Primrose Work Orders 2003          
Completed             Received  
Month Year Day Billed Completed Description Unit # Ticket # W.O. Description Day Month/Year
Nov 03 5   Cleaned all gutters and inspected roofs on bldg 3 Bldg 3   Clean gutters and inspect roofs 5 Nov 03
Nov 03 26   Cleaned all gutters and inspected roofs on bldg 5 Bldg 5   Clean gutters and inspect roofs 26 Nov 03
Nov 03 5   Cleaned all gutters and inspected roofs on bldg 4 Bldg 4   Clean gutters and inspect roofs 5 Nov 03
Nov 03 5   Cleaned all gutters and inspected roofs on bldg 3 Bldg 3   Clean gutters and inspect roofs 5 Nov 03
Nov 03 19   Repaired dumpster gate at bldg 9 & 5 Grounds   Dumpster gate at bldg 9 & 5 19 Nov 03
Nov 03 26   Cleaned out gutters at 53,55,57 57 363 H/O reports that the gutter bet unit 57 and unit 55 is clogged.pls clean and repair if necessary 24 Nov 03
Nov 03 26   Put flashing to divert water-fixed gutter-power washed back of unit and walkway 110   Gutter clogged and walkway needs powerwashing 26 Nov 03
Nov 03 19   Cleaned and repitched gutter 9   Check gutter for leaks-seal if you have too 19 Nov 03
Nov 03 19   Repaired fence around several dumpsters Grounds 361 During the recent storm the fence by the dumpster became loose,pls inspect and make any repairs that are necessary. 18 Nov 03
Nov 03 19   Bent gutter back to shape and nailed in place Grounds 359 Gutter above office door is loose.pls resecure 14 Nov 03
Nov 03 19   Cleaned up garbage and resecured wood on dumpster fence Grounds 360 During site inspection several dumpster areas were littered with large items-the dumpsters by bldg 8 & 13 were esp bad. Pls clean these areas and remove all large items.if this is a problem contact me 14 Nov 03
Nov 03 26   Replaced shingles that blew off in storm 140 358 H/O reports that shingles blew off roof during recent storm.pls replace shingles 14 Nov 03
Nov 03 19   Drilled hole and resecured railing with concrete screws 26 356 H/O reports that the railing on the deck needs to be resecured at present it is not attached.pls reattach 6 Nov 03
Nov 03 5   Cleaned gutters and inspected roofs Bldg 4   Clean gutters and inspect roofs 5 Nov 03
Nov 03 5   Applied water proofing material to basement wall 11-5 drilled hole for sump pump 11-8 102   Drill hole for sump pump and apply water proofing to basement wall 3 Nov 03
Nov 03 21   Completed the compound on the wall that had damage 76 357 As per our discussion on 11-5 pls repair the damage caused to the sheetrock in the rear bedroom from the roof leak. 10 Nov 03
Nov 03 5   No cricket was removed from the roof-roof was put back to original state after repair was made 76 354 Pls inspect unit ASAP to see if there was a roof cricket that was removed and never reinstalled 3 Nov 03
Nov 03 19   Caulked crack in firewall and caulked roof line 63 353 H/O reports that there is a roof leak above the back bedroom-pls repair the roof 3 Nov 03
Nov 03 5   Gutter was cleaned out 10-31 gutters were checked and all is fine 9 349 H/O reports that the gutter must be repaired-pls make any repairs that are necessary 3 Nov 03
Nov 03 26   Caulked valley and tared area 139   Lisa called in to say that the basement was leaking 12 Nov 03
Nov 03 19   Nailed several pieces of wood around fence by dumpster at bldg 1 Grounds 350 Pls resecure the fence around the dumpster near bldg 1-in addition pls clean all dumpster areas,espically those near bldg 1,2,7 & 15-upon inspection there are several items that need to be disposed of. 24 Oct 03
Nov 03 21   Cleaned debris and garbage Grounds 362 During the inspection 11-19 several dumpsters were not being cleaned. Pls make sure all dumpster areas are clear of garbage and debris-esp the dumpster near bldg 15. 20 Nov 03
Nov 03 26   Installed a 2 inch build up around window 125   Need to build up near lip of window well 11 Nov 03
Nov 03 10   Replaced the concrete in the back of the unit where the basement problem was corrected 102   Replace concrete in back of unit   Nov 03
Dec 03 3   Cleaned around dumpster -2 bins jam packed-put some garbage in bin 3 and sorted through Grounds   Dumpster by bldg 15-pls sort through the garbage and put where it is susposed to be 25 Nov 03
Nov 03 10   Replaced concrete sidewalk that was removed during water pipe replacement 27 337 Replace concrete sidewalk that was removed during water pipe replacement 26 Sept 03
Dec 03 19   Cleaned out contaiminated trash Grounds 368 Recycling dumpsters are contaiminated with trash-pls remove the trash during the clean up on fri and place in the proper dumpster 18 Dec 03
Dec 03 17   Reattached leader to gutter and cleaned out 56 367 H/O reports that the leader from the gutter has fallen.pls repair and clean out gutter 18 Dec 03
Dec 03 17   Cleaned all gutters and roof inspections Bldg 10   Clean gutters and inspect roofs 15 Dec 03
Dec 03 17   Cleaned all gutters and roof inspections Bldg 9   Clean gutters and inspect roofs 15 Dec 03
Dec 03 17   Cleaned all gutters and roof inspections Bldg 8   Clean gutters and inspect roofs 15 Dec 03
Dec 03 10   Repitched gutter and reattached siding that was hanging 107 365 H/O reports that water is leaking from the gutter and this has caused the siding to separate from the bldg.pls inspect and repair 9 Dec 03
Dec 03 10   Reattached leader and put new screws to secure 23 364 H/O reports that the drain pipe has fallen away from the bldg.pls repair asap 9 Dec 03
Dec 03 17   Cleaned all gutters and roof inspections Bldg 7   Clean gutters and inspect roofs 3 Dec 03
Dec 03 10   Cleaned all gutters on blds 6 and checked roofs Bldg 6   Clean gutters and inspect roofs 3 Dec 03
Dec 03 10   Installed cover over exposed wires 104   Wires are exposed on unit-Lisa called this in 2 Dec 03
Dec 03 3   Put wire mesh inside hole of 2 vents on back of house 102   Put grill over vents to prevent animals to enter 2 Dec 03
Dec 03 3   Cleaned around dumpster -2 bins jam packed-put some garbage in bin 3 and sorted through Grounds   Dumpster by bldg 15-pls sort through the garbage and put where it is susposed to be 25 Nov 03
Dec 03 10   Replaced 2 spot lights Bldg 1   Light on bldg is out pls replace 25 Nov 03
Dec 03 10   Cleaned window wells,silconed windows and put 2 new window well covers and sealed 58 351 H/O reports that basement leaks .pls inspect and advise mgmt what can be done h/o also reports that door saddles need replacing. Pls inspect this also and advise why they need replacing 24 Oct 03
Dec 03 17   Cleaned out gutters and now water is draining properly 171-173   Gutter clogged over flowing right over 175 window adding to problem 17 Dec 03
Dec 03 17   Dug trench around well put 2 bags of 80lb stone and new window well cover 175   Window well 17 Dec 03
Jan 04 7   Policed grounds and cleaned debris Grounds   Clean grounds of debris 7 Jan 04
Jan 04 7   Fixed cement at unit 102   Cement needs to be fixed 7 Jan 04
Jan 04 7   Fixed phone box 134   Phone box needs to be fixed 7 Jan 04
Jan 04 7   Caulked around door as per H/O 128   H/O asked to have door caulked 7 Jan 04
Jan 04 7   Renailed gutter 50   Gutter falling 7 Jan 04
Jan 04 7   Renailed gutter 51   Gutter falling 7 Jan 04
Jan 04 7   Refastened loose A frame 67   Front A frame loose 7 Jan 04
Jan 04 7   Unclogged leader that was clogged 25   Leader clogged 7 Jan 04
Jan 04 7   Renailed gutter 4   Gutter falling 7 Jan 04
Jan 04 7   Renailed gutter 21   Gutter falling 7 Jan 04
Jan 04 7   Reset unlocked siding 23   Siding unlocked 7 Jan 04
Jan 04 7   Fixed bent gutter 74   Gutter bent 7 Jan 04
Jan 04 7   Reset unlocked siding front and rear 98   Siding unlocked front and rear 7 Jan 04
Jan 04 7   Renailed gutter and bent back 120   Gutter falling 7 Jan 04